MANUFACTURING PROCESS OF BARS
1. Insulation
Check
For
the manufacturing of stator bars insulated copper conductors are brought from
Bangalore, it’s of two type’s i.e. solid copper conductor & hollow copper
conductors which are used in water cooled stator layer glass insulation.
·
Insulating materials and the conductors
are ensured to be certified.
·
If required the insulation is checked by
the respective agencies.
2. Conductor
cutting & End Cleaning
This
process is done by automatic CNC machine. In this process the pre-insulated
copper conductor is cut into number of pieces of required length (length given
in drawing as per design) insulation is removed from both ends of the copper
conductor. 800MW bar contains 60 strands 50 solid Cu strands and 10 hollow
stainless steel strands.
3.
Transposition
Transposition
means changing/shifting of position of each conductor in active core (slot)
part. After cutting the required number of conductors, the conductors are
arranged on the 12 comb in staggered manner and then bends are given to the
conductors with the help of bending die at required distance. Then the
conductors are taken out from the comb and die and placed with their ends in a
line and transposition is carried out. This process is repeated for making
another half of the bar which would be mirror image of the first half. The two
halves of the bar are overlapped over each other and a spacer is placed between
the two halves.
Transposition
is done in two ways:
·
Half Pitch Transposition: - In this
transposition, the first conductor at one end of the bar becomes the last
conductor at the other end of the bar.
·
Full Pitch Transposition: - In this
method of transposition, the first conductor at one end of the bar becomes the
last conductor in the mid of the bar and then again becomes the first conductor
at the other end of the bar.
Need
of Transpostion
1. To
reduce eddy current losses.
2. Equalize
the voltage generator.
3. To
minimize skin effect of ac current, small cross section of conductor is used.
4. Crossover insulation
The
pre insulation of the copper conductor may get damaged due to mechanical bending
in die during transposition, hence the insulating spacers are provided at the
crossover portion of the conductors. A filler material (insulating putty of
molding micanite) is provided along the height of the bar to maintain the
rectangular shape and to cover the difference of level of conductors. To
eliminate inter turn short at bends during edge wise bending and leveling of
bars in slots portion for proper stacking.
5. Stack Pressing
This
process is basically done to consolidate the solid as well as the hollow
conductors into a single bar, the insulating material provide at crossover
positions which has gluing properties melts and helps in the proper
consolidation of the bar. In this process the bar is pressed both vertically
and horizontally in the Pressing Machine. The pressing machines are also
provided with the heaters Each bar is loaded on each tier of heating plate and
it is then provided with an initial pressure of 35±5 kg per cm2 and an initial
temperature of 100-110° C. then the temperature is allowed to raise to the
maximum of 160°C, this temperature is kept for at least one hour with a final
pressure of 80±10 kg per cm2 vertically and 70±10 kg per cm2 horizontally.
After pressing the bar at specified pressure and maximum temperature for one hour,
the bars are then cooled placing them on cooling plates through which water is
allowed to follow below 50°C. The cooled bars are checked for their heights and
widths at pressed portion of the bar. This complete process performed above is
for one half of the bar. The same process is then repeated for the other half
of the bar similarly and then checked for bar’s height and width at pressed
portions as done before. Then the ends of both the bars are cleaned with
rectified spirit and sand paper for the inter strand test.
6. Inter Strand Short test
The
consolidation bar stack is tested for the short between any two conductors in
the bar, if found then it has to be rectified. This is done to ensure that no
local current is flowing due to short circuit between conductors. (300V A/C
supply). For this test all the bare conductors at both the ends are separated
from each other so that they do not short circuit. Then a live wire is
connected to a conductor and received from it consecutive conductor to light a
lamp. Hence if the lamp lights up it shows short circuit between the two
conductors due to improper insulation between them. . It shows insulation
failure between the conductors, these conductors are then replaced and bar is
followed through all the previous processes. Similarly all the conductors are
checked for any short circuit. After passing both the half bars from I.S.T. the
bars are combined together and pressed into a single bar. A sheet of mica glass
insulation is provided between the two halves as the insulation also has some
gluing property to consolidate the two halves into a single bar. All the steps
of pressing are again followed for the complete bar and then it is allowed to
cool.
7. Forming
In
heavy generators each stator coil is very large in size and hence its
manufacturing is difficult as it will be very difficult to handle and process
the complete coil. So each coil is manufactured in two halves i.e. Upper half
and Lower half. The bars which are processed till this process are straight and
hence they are required to be formed into the upper half or the lower half.
Hence this process of forming is very important as in this process the bars are
bending from both the ends of the bar i.e. at exciter side and turbine side at
specific angles and shape as per design. This process is done manually. First
the former is set according to the design making different angles at different
positions. Each bar of a variant is bent or formed at same angle. Once the
former is set, the bar is mounted on it and formed manually by melleting it
from both the ends. After forming the formed portion of the bars are assumed to
get loose creating air gaps between the conductors due to such a heavy melleting.
Thus the formed portion of the bar are clamped at different places and provided
with heaters to reconsolidate the formed portion. After few hours the bar is
then allowed to cool at room temperature.
8. End Conductor Cutting
Due
to heavy malting of the bar for forming it from both the side i.e. exciter side
and turbine side, the conductors of the bar are produced at the ends of the
bar. Therefore to bring all the conductors of the bar in a plane End Conductor
Cutting is required to be done. Both the solid and hollow conductors are cut
and from both the sides of the bar. Also this process of cutting of the hollow
conductors helps in opening of vents of hollow conductors from both the ends of
the bar.
9. Pickling Process
After
the forming and cutting process of the bar and due to the transportation of the
bar, there accumulate very minute particles of dust on the ends of the bar.
These particles may cause hindrances at the time of brazing and may create some
air gaps. So, in order to remove these unwanted particles, basically the oil
particles pickling process is performed. The basic solution used for this
process is called pickling solution.
The constituents of the pickling
solution are:
·
Sulphuric acid (H2SO4)-10%
·
Phosphoric acid (H3PO4)-5%
·
Hydrogen peroxide (H2O2)-5%
·
Water (H2O)
There are many other solutions used
in this process, these are:
·
Ammonia
·
Thinner
·
Water
·
Rectified spirit
·
Nitrogen
In this process the following steps
are involved:
·
The end of the bar is dipped in thinner
to remove the dust or oil particles.
·
The end is then dried with the help of
N2 gas.
·
Then the bar end is dipped in pickling
solution for 5 to 10 minutes.
·
This is then followed with dipping in
water.
·
As there is acid in the pickling
solution, so accordingly to neutralize the acidic effect of the acid it has to
be treated with some base, so the bar is then dipped in Ammonia (10%).
·
It is then followed with dipping in
water.
·
As water takes a lot of time to
evaporate, it may let the tiny chemical particles on the bar to react with it
and leave spots on the bar, this may weaken the insulation at those particular
points and thus damage it, further it may lead to poor brazing. So in order to
avoid such a damage the bar is dipped in rectified spirit to make the water
contents evaporate as soon as possible.
·
Then the bar is dried with N2 gas.
·
Finally it is wrapped with cotton cloth
to avoid any manual touch with may deposit any dust particle on it until it is
ready for brazing. The same process of pickling then performed on the other end
of the bar.
10. Contact Sleeve Mounting
After
the pickling process is complete, contact sleeve and water box bottom parts are
mounted on both the ends of the bar. Contact sleeve, as clear from the name
itself, it is a rectangular sleeve which is used to make contact between upper
and lower bars when laid out in the generator to form a complete coil. All the
solid conductors are cut from the ends of the bar after the contact sleeve
except the outer solid conductors. None of the conductor is cut before the
contact sleeve so that to make proper contact between the upper and the lower
bars. The water box is mounted in two halves; first the water box bottom part
is mounted after the contact sleeve keeping some distance between them. Both
the ends of the bar are then again pickled along with contact sleeve and water
box bottom part following the same procedure of pickling.
11. Brazing of coil lugs
For water cooled
generator bars, the electrical connection contact and water box for inlet and
outlet of water are brazed. The contact sleeves, which are used to make contact
between the upper bar and the lower bar to form a complete coil and the water box
bottom part, both together are called Coil Lug, so the brazing of these two
parts at the end of a bar is called Coil Lug Brazing. Brazing is basically the
process of fixation of both the contact sleeve and water box bottom part or we
can say both are properly consolidated using brazing material at high
temperatures. Consolidation is properly done so that no air gap is left which
would adversely affect the conducting properties of the contact sleeve and the
bar.
The
two types of brazing processes are:
·
Thermal brazing (using LPG)
·
Induction brazing :
As induction brazing is more beneficial than
thermal brazing as it does not requires any inflammable gas for heating. So now
a day’s Induction brazing process is used. For brazing as we use very high
temperature so that is possible due to carbon strips fixed on the brazer.
Carbon has very high resistance and when the current is allowed to pass through
it due to induction the material to be brazed i.e. Contact Sleeve gets super
heated. Induction heating is hence faster and even more efficient than thermal
heating.
When
the contact sleeve becomes red hot at 750ºC, the brazing material is then
pushed to fill the air gaps and to consolidate the contact sleeve on the bar.
It is then allowed to cool.
The
types of brazing materials used are:
·
LAG 15P ( Alloy Silver 15 Phosphorous)
·
LAG 40Cd ( Alloy Silver 40 Cadmium)
Same
process of brazing is then repeated for the water box bottom part. After the
brazing of water box bottom part the bar is then allowed to cool at room
temperature.
·
We also use teal wielding in 800 MW
stator bar.
12. End Conductor Cutting
As is clear from the
name itself this is the process of cutting of extra conductors i.e. the hollow
conductors left after the water box bottom part are cut from both the ends of
the bar. These conductors are required to be cut so that water box top part with
a nozzle is to be mounted on the water box bottom part. The vents of the hollow
conductors are visible from the ends of the water box bottom part. The openings
of the vents of the hollow conductors are then checked to be uniform. After
cutting of extra conductors from both the ends of the bar, pickling process is
done. Same pickling process as mentioned before is then done at both the ends
of the bar for removing the dust particles, oil particles and other unwanted
impurities which we assume to be there after the brazing process of the contact
sleeve and water box bottom part. After pickling the bar ends are then wrapped
in cotton cloth until the water test is performed.
13. Water Flow Test
Water flow test is
performed so that there not any blockage in the vents and also to check the
flow of water. Flow should be uniform i.e. all the vents should have same water
flow. In this test water is supplied from one side of the bar and is collected
from the other side of the bar in a tank and is supplied back to the first end.
Flow of the water is checked by measuring the distance of the flow of water. If
there is any kind of blockage inside the hollow conductors of the bar then it
is indicated by flow of water i.e. flow of water will be not uniform and the
bar is assumed to be chocked. Then cocked conductors are changed or repaired
and the bar is reformed and water test is again performed to check the flow of
water.
14. Brazing Of Water Box Top Part
Brazing of water box
top part is done with water box bottom part in brazing section of Block-4.For
this it should be kept in mind that water box bottom part should have same
material as that of water box top part. The difference in previous brazing and
this brazing is that, now flux is also introduced with brazing material and
also flux is mixed with copper chips. Copper chips are added to make the
electrical contact between the top and bottom part without the copper chips
this will be not possible. In this brazing material is formed in the shape as
that of water box side where it has to be brazed. Brazing material is formed in
square shape for top and bottom part and in ring shape for the brazing of
nozzle for water flow. Then both the parts are heated with induction brazer as
done earlier. It is heated until they become red hot then the brazing material
melts due to its low melting temperature then the melting temperature of the
water box top and bottom part. Brazing material is also introduced at the
boundaries until it is completely consolidated that is the entire air gap is
completely filled. After the brazing of water box top part the bar is then
allowed to cool at room temperature.
15. Nitrogen Leak Test
As the name suggests
Nitrogen gas is the main constituent of the test. This test is similar to
puncture test that is inflated tube is dipped in water for any leakage, the air
bubbles gives us the exact position of the puncture. Similarly on the same
steps this test is performed. Basically this test is performed to check any
leakage in bar i.e. to check the brazing. In this test nitrogen at a pressure
of 10Kg/Cm2 is forced from one end of the bar and other end of the bar is
blocked then the pressure of 10Kg/Cm2 is maintained and both the ends of the
bar are dipped in water. The bubbles if there any tells us that brazing is weak
or not done properly. So if bubbles appear then brazing is done again and same
test is performed for the proper brazing of water box top and bottom part. Then
both the ends of the bar wrapped in cotton cloth so that it is not disturbed
i.e. to 18 avoid any manual touch which may deposit any dust particle on it
until it is ready for brazing.
17. Internal Pickling
After various test
performed on the bar the pickling process i.e. removal of any dust particles
lubricants etc is done only on outer surface of the bar (ends). But from inside
it is assumed that there must be some impurities, foreign material must be
present. For this purpose inside pickling is done.
As mentioned earlier
same process is repeated but from inside of the hollow conductors this time.
In this process the following steps
are involved:
·
The thinner is passed through the bar to
remove the dust or oil particles.
·
The dried with the help of N2 gas.
·
Then the pickling solution is passed for
5 to 10 minutes.
·
Then water is flowed in the bar.
·
As there is acid in the pickling
solution, so accordingly to neutralize the acidic effect of the acid it has to
be treated with some base, so the bar is filled with Ammonia (10%).
·
It is then followed flowing of water
again.
·
As water takes a lot of time to
evaporate, it may let the tiny chemical particles in the bar to react with it
and leave spots in the bar, this may weaken the insulation at those particular
points and thus damage it, further it may lead to poor brazing. So in order to
avoid such a damage the rectified spirit is flowed in the bar to make the water
contents evaporate as soon as possible.
·
The bar is then dried with N2 gas.
·
Finally it is wrapped with cotton cloth
to avoid any manual touch which may deposit any dust particle on it until it is
ready for brazing.
18. Baroscopic Test
This test is performed
to check the impurities or foreign material inside the bar. To look inside with
naked eye is not possible so we use baroscopic for this purpose. So after
internal pickling we use a baroscopic to look inside the bar. Baroscopic is
having a probe having a LED (light emitting diode). LED is used to provide
light inside the bar. The probe of the baroscopic is inserted from one end of
the bar and seen from a magnifying lens. The probe gives a light which is
reflected by the sides of the bar (inside) and with the help of magnifying lens
we get a clear image that what is there in the bar. If impurities are present
then these are removed then only after the bar is send to next operation.
19. Water Test
Here again water test
is performed. In earlier water test water flow was checked without the water
box top part. But now the top part is brazed to the bottom part and to check
its flow this test is performed. Also to check the proper flow from the nozzle
this test is performed. In this test water is forced or pushed from one end of
the bar and flow of water is checked from other end of the bar. This test tells
us the presence of any choke vents of water box top part. If any choke vent is
present then it is repaired or whole of the water box top part is changed with
new one
20. Thermal Shock Test
Thermal shock test is
performed to check whether the bar can withstand extreme conditions i.e. when
the generator is working or running at about 3000 Rpm. This is achieved by
thermal shock test. Thermal shock test consist of series of hot water & cold
water cycles alternatively. So firstly hot water at temperature of about 90ºC
is passed through the bar and then cold water at about room temperature 27ºC
approx. is flowed inside the bar alternatively. This process is repeated again
and again. This process is repeated for about 26 times i.e. it has 26 cycles of
hot and cold water. So this test tells us the strength of the bar so that it
can withstand the working conditions of the generator. Temperature of the bar
is taken in account according to the working temperature of the generator. The
cycles of hot (800C) and cold (300C) water are flown through the bar to ensure
the thermal expansion and contraction of the joints.
21. Helium Leakage Test
Helium test is the most
important test of all, because helium test is performed to check any minute
leakage within the bar and at the brazed portion. Any minute leakage which
couldn’t be checked by water test can easily be observed by helium test because
helium is one of the lightest gases. So this is also the customers check point,
before performing this test customer is by called and they see themselves the
test being performed and if They find the test all right then only the bar is
send to next process. In helium test, whole of the bar is wrapped in the
polythene excluding the end points. The helium gas at pressure of 11Kg/Cm2 is
passed through the bar and a probe connected to the gauge is inserted inside
the polythene at different places. The gauge will show deflection if there is
any helium atom present. Gauge will show reading even if 1 helium atom in
100000 atoms is present. This test checks the strength of brazing and
insulation.
22. Reforming
After
all the previous processes which had undergone on the bar it is assumed that
the shape of the bar is deformed from its original shape due to handling of the
bar from one place to another for different processes. So to keep the shape of
the bar as per design, the bar is checked if it is found distorted then it is
reformed in the previous former machine by placing the bar on the former and
malleting.
23. Insulation
The
bar is insulated with the given number of layers to build the wall thickness of
insulation subjected to the generating voltage of the machine. Insulation is
basically done to prevent any kind of short circuit between the bar and the
stator core when the bar is assembled in the stator of the machine. The stator
bars are insulated with Micalastic (trade name) insulation. High quality mica,
selected epoxy resins and a matching vacuum impregnation process are the
characteristic features of the micalastic insulation for large turbo
generators.
The
bar is provided with 14 layers of insulation. Out of these fourteen layers, 12
layers are provided by using a machine called CNC TAPPING MACHINE manufactured by a company named MICAMATION. The rest of the two layers
are provided manually.
The
insulating material varies as according to the rating of the machines as
follows:
·
For
800 MW : Mica Splitting Tape
·
For
THRI : Mica Glass
During
machine taping in the slot portion the transition from machine to hand taping
is adjusted at the start of the bend for a tape width for every layer from bar
center. After about half the number of layers, the taping is to be started
further at the bend. The mica tape consists of a thin high strength baking
material to which the mica is bounded by synthetic resin. The number of layers
i.e. the thickness of insulation is determined by the voltage of the machine.
24. Impregnation & Baking
A. Thermo reactive System: In case of
rich resin insulation the bar is pressed in closed box in heated condition and
baked under pressure and temperature as per requirement for a given period.
B. Micalastic System : In case of poor
resin system the insulated bars are heated under vacuum and the impregnated
(dipped) in heated resin so that all the air gaps are filled, layer by layer,
with resin. Then extra resin is drained out and bars are heated and baked under
pressed condition in closed box fixture.
C. VPI Micalastic System: - The bars
already lay in closed fixture and full fixture is impregnated (dipped) in resin
and then fixture with box is baked under given temperature for given duration.
D.
VIP Micalastic System: - The individual (Separate) bar is heated in
vacuum and impregnated in resin. Then bar is taken out and pressed in closed
box fixture and then baked at given temperature for given duration.
25. Micalastic Insulation and Impregnation
For
insulation with micalastic, the conductor strands are arranged together to form
a compact assembly and set to the required shape. This assembly is then baked
with epoxy resin to give it mechanical strength required for further
processing. The bars are then dried under vacuum and impregnated with synthetic
resin, which by reason of its low viscosity penetrates the insulation
thoroughly and eliminates all voids. After impregnation under vacuum, the bars
are subjected to pressure, with nitrogen being used as pressurizing medium. The
impregnated bars with direct conductor cooling are then brought to the required
dimensions in moulds and cured in an oven at a high temperature. This complete
process involves pressing of the bars, drying by heating, impregnation in resin
and finally curing. These processes are discussed briefly below:
·
Pressing:
The bars are pressed to bring them back to the original dimensions.
·
Drying:
The stator windings are to be dried under vacuum 0.1 m bar at (60±5) °C for 15
hours, minimum. The drying temperature is to be increased to (65±2) °C if the
initial viscosity of the impregnating resin mixture is high. The temperature
distribution should be as uniform as possible. The drying under vacuum can be
stopped if the pressure rises, 10 minutes after closing of vacuum valve is less
than 0.06 m bar.
·
Impregnation:
The impregnation resin mixture is to be heated in the working tank, to (60±3)
°C or in case of higher initial viscosity. At a temperature of 50ºC, the
impregnating resin mixture is to be degassed with 1-5 m bar vacuum.
Subsequently the stator windings are to be dipped continuously in resin
hardener mix such that the highest locations of the windings are at least 100
mm below the resin level. After 10 minutes of resin stabilization, pressure is
increased by application of nitrogen. Pressure is to be gradually increased in
uniform stages within 80 minutes to 4 bars and to be maintained for 120 minutes
in the impregnation tank. The impregnation of the stator winding is to be
monitored continuously. Further it is to be decided whether to increase the
pressure or to stop the impregnation process, however the total period of
nitrogen pressure cycle shall in any case not exceed 4 hours. The impregnation
tank during shut down is to be closed and kept either filled with nitrogen
(1.1bar) or low vacuum.
·
Curing:
To
prevent heating in the overhang portion, the curing of the impregnated stator
winding is to be done with a maximum 160°C hot air. The curing period is
extended for such a long time till the measurement positions in the core
indicate (140±5) ºC for
minimum 8 hours.
26. Finishing
The
baked and dimensionally correct bars are sanded - off to smoothen the edges and
the surface is calibrated, if required, for the dimension.
27. Conducting varnish coating:
1.
OCP
(Outer Corona Protection) Coating:- The black
semi-conducting varnish coating is applied on the bar surface on the core
length.
2.
ECP
(End Corona Protection) Coating:- The grey
semi-conducting varnish is applied at the bend outside core end of bars in
gradient to prevent from discharge and minimize the end corona.
Resin System:-
a)
Rich resin or
Thermo reactive insulation system:- In this type of insulation system the
bond content in resin is 35-37%. The raw materials are ready to use and require
preservation and working on temperature 20-250C. Its shelf life is one year
when kept at temperature 200C which could be increased when kept at temperature
of 50C.
b)
Poor
resin or Micalastic insulation system:- In this type of
insulation the bond content in the resin is 5-7% and insulating material is
prepared with accelerator treatment. The temperature control need not required.
The insulating material is applied on job and then the same is impregnated
(fully dipped) in the resin.
Testing:-
When
the bar is dried it is wrapped with aluminum sheet to make outer surface of the
bar conducting so that tan δ and H.V. (High voltage test) can be performed.
After these tests the coating of red gel is applied at both the ends of the
bar.
28 .TanΔ Test
This
Test is performed to find the capacitance of the bar because bar will act as
capacitor when it is laid in the stator of the generator. In this test
Schearing Bridge which works on the principle of wheat-stone bridge is used to
find the unknown capacitance of the bar. For good efficiency, capacitance of
the bar should be high but we never approach pure capacitance.
In
this test also same bar which is wrapped with aluminum is used to make the bar
conductive throughout the outer surface of the bar. The two conducting material
i.e. the aluminum sheet and the conductors of the bar act as two plates of the
capacitor and the insulation on the bar act as dielectric medium for the
capacitor. The capacitance of the bar is found and of angle of deviation due to
impurity in the insulation is obtained from the formula: C4 * R4 * 10-4 = tan δ
For different ratings of the bar the acceptable value of tan δ is fixed
according to their insulation requirement as per design considerations.
29. H.V. (High Voltage) Testing
This
test is also known as insulation test because this test is performed to check
the insulation of the bar. In this test the bar which is already wrapped with
aluminum is used. High voltage is applied to the bar using auto-transformer and
it is increased in steps according to the working voltage of the generator. If
the insulation is weak the bar will puncture at the place of weaker insulation.
For 800 MW the working voltage of the bar is 82.5 KV. If any of the bar fails
this test i.e. bar is punctured at any point then the bar is sent back for
re-insulation and all the processes are repeated again.
30. Dispatched For Winding
The bars preserved
with polythene sleeve to protect from dust, oil , dirt , rain etc. Then the
bars are send to Block-1 for winding of turbo and hydro g
2 comments:
Thanks for Shearing This Post
AR Engineering is a Manufacture and Supplier Of Transformer Oil Filtration Plant, Industrial Oil Purification System, Trickle Impregnating Machine and Vacuum Pressure Impregnation Plant.
Industrial Oil Purification System
Vacuum Pressure Impregnation Plant
Batch Type Trickle Impregnating Machine
Index Type Trickle Impregnating Machine
Trickle and Roll Dip Impregnation Machine
Single Stage Transformer Oil Filtration Plant
Two Stage Transformer Oil Filtration Plant
Nice articles and your information valuable and good articles thank for the sharing information Oil Filtration Plant
Post a Comment